10 to 12 months

First fix for the electrical, mechanical and internal structural joinery elements of the house to continue, all underfloor heating to be installed and sub floors to be finished off, all external doors to be fitted, plastering to commence, further works to the external areas, internal specification items to be ordered and confirm lead times, external painting to continue.